Installing new electrical infrastructure to the airport’s visual approach systems required overnight work in a remote village, with the runway needing to reopen for operations every morning.
Installed new raceways, vaults, and conductors from the FAA equipment building
Tied in to the existing PAPI and REIL systems
Completed all work overnight to avoid disrupting daily flights
Upgraded visual approach systems delivered on a tight overnight schedule
Zero disruption to daily flight operations